Spiral conveyor systems used in cooling, freezing, proofing, heating, drying,
curing, pouch cooling, accumulating, elevating and lowerating. Spirals, Spiral
freezers,Spiral coolers, Spiral pouch coolers, Used spirals, Bakery spirals,
Spiral systems, Spiral conveyors, Spiral dryers, Blast freezers, Freezers,
Coolers, Chillers, Conveyors, Spiral refrigeration, Spiral proofers, Spiral
belts, Bakery coolers, Cookie coolers, Bun coolers, Pouch chillers, Refrigeration,
Spiral consultants, Spiral engineering, Used spiral freezers, Used spiral
coolers, Tunnel freezers, Refrigeration systems Accumulating,
Ambient coolers, Bakery coolers, Bakery spirals, Blast freezers, Bun coolers,
Cake coolers, Chillers, Conveyors, Cookie coolers, cooling, Dough freezers,
Elevating, Food equipment, Freezing, Freezing, Pouch chillers, Pouch coolers,
Proofing, Refrigeration, Refrigeration systems, Spiral, Spiral accumulating,
Spiral belts, Spiral bread coolers, Spiral consulting, Spiral conveyors, Spiral
cooling, Spiral dryers, Spiral engineering, Spiral freezers, Spiral ovens,
Spiral pouch coolers, Spiral refrigeration, Spiral systems, Spirals, Tunnel
freezers, Used spiral coolers, Used spiral freezers, Used spirals, IJ White,
Advanced, Aero, CBI, RMF, GF systems
|
|
|
|
|
 |
 |
|

|
All You Need To Know Archives
Installation Timelines for Spiral Systems
You asked us for normal timelines for installations of various spiral systems, so here they are:
|
Single ambient cooler
|
5 Days, see note #1
|
|
Dual ambient cooler
|
9 Days, see note #2
|
|
Refrigerated cooler
|
13 Days, see note #3
|
|
Freezer
|
15 Days, see note #4
|
|
Proofer
|
13 Days, see note #5
|
Notes:
#1- Installations start from when the truck is ready to be unloaded and includes all mechanical installation of the spiral. Time for electrical has to be added(use 2 days), control panel arrives pre wired. Includes install of both infeed and discharge conveyors.
#2- Installations start from when the trucks are ready to be unloaded and includes all mechanical installation of the spiral and infeed and discharge conveyors. Time for electrical has to be added (use 3 days), control panel arrives pre wired.
#3- Installation start from when the truck is ready to be unloaded and includes all mechanical installation of the enclosure, spiral, coils, fans, baffle walls, lighting, infeed and discharge conveyors. Time for electrical has to be added(use 4 days), control panel arrives pre wired. Does not include piping or high side equipment
#4- Installation starts from when the truck is ready to be unloaded and includes all mechanical installation of the enclosure, spiral, coils, fans, baffle walls, lighting, infeed and discharge conveyors. Time for electrical has to be added(use 5 days), control panel arrives pre wired. Flooring has to be ready and suitable for freezer conditions(cured for 30 days). Does not include piping or high side equipment
#5- Installation starts from when the truck is ready to be unloaded and includes all mechanical installation of the enclosure, spiral, air handling system, ductwork, lighting, infeed and discharge conveyors. Time for electrical has to be added(use 2 days), control panel arrives pre wired.
The above times are standard and normal and can be met 95% of the time. If you need shorter times additional people can be added. Flooring for freezers has to be pre planned and can be pre-poured. Non skid protective coating is recommended over stainless steel.
Electrical time addition is dependent on local codes and customer preferences as to conduit, wiring, controls. On your next spiral project which requires good planning, a written timeline which will be met, and quick installation times, give us a call.
|

|
 |
 |
|
|
 |